﻿# Gantt: Baselines

Show planned vs. actual schedule side by side using baseline bars.

Keywords: gantt, baseline, planned, actual, schedule, comparison

> API reference: [RadzenGantt API](https://blazor.radzen.com/docs/api/Radzen.Blazor.RadzenGantt-1.md)

## Examples

## Blazor Gantt Baselines

Set `BaselineStartProperty` and `BaselineEndProperty` to display planned vs. actual schedule. The gray bar behind each task bar represents the original plan.

```razor
<RadzenGantt @ref="gantt" TItem="GanttTask"
             Data="@tasks"
             IdProperty="@nameof(GanttTask.Id)"
             ParentIdProperty="@nameof(GanttTask.ParentId)"
             TextProperty="@nameof(GanttTask.Name)"
             StartProperty="@nameof(GanttTask.Start)"
             EndProperty="@nameof(GanttTask.End)"
             ProgressProperty="@nameof(GanttTask.Progress)"
             BaselineStartProperty="@nameof(GanttTask.BaselineStart)"
             BaselineEndProperty="@nameof(GanttTask.BaselineEnd)"
             Style="width: 100%; height: 480px;">
    <Columns>
        <RadzenGanttColumn Title="Task" Property="@nameof(GanttTask.Name)" Frozen="true" Width="200px" />
        <RadzenGanttColumn Title="Start" Property="@nameof(GanttTask.Start)" Width="110px" FormatString="{0:d}" />
        <RadzenGanttColumn Title="End" Property="@nameof(GanttTask.End)" Width="110px" FormatString="{0:d}" />
        <RadzenGanttColumn Title="Progress" Property="@nameof(GanttTask.Progress)" Width="100px" FormatString="{0}%" />
    </Columns>
</RadzenGantt>

<div class="rz-mt-4">
    <RadzenText TextStyle="TextStyle.Body2">
        <span style="display:inline-block;width:14px;height:8px;background:var(--rz-text-disabled-color);opacity:0.45;border-radius:4px;vertical-align:middle;margin-inline-end:4px;"></span>
        Gray = original planned schedule &nbsp;|&nbsp;
        <span style="display:inline-block;width:14px;height:8px;background:var(--rz-primary);border-radius:4px;vertical-align:middle;margin-inline-end:4px;"></span>
        Blue = current actual schedule
    </RadzenText>
</div>

@code {
    RadzenGantt<GanttTask> gantt;
    List<GanttTask> tasks;

    protected override void OnInitialized()
    {
        var today = DateTime.Today;

        tasks = new()
        {
            new()
            {
                Id = 1, Name = "Project",
                Start = today.AddDays(-2), End = today.AddDays(28),
                BaselineStart = today, BaselineEnd = today.AddDays(24),
                Progress = 40
            },
            new()
            {
                Id = 2, ParentId = 1, Name = "Foundation",
                Start = today.AddDays(-2), End = today.AddDays(5),
                BaselineStart = today, BaselineEnd = today.AddDays(4),
                Progress = 100
            },
            new()
            {
                Id = 3, ParentId = 1, Name = "Framing",
                Start = today.AddDays(5), End = today.AddDays(12),
                BaselineStart = today.AddDays(4), BaselineEnd = today.AddDays(10),
                Progress = 60
            },
            new()
            {
                Id = 4, ParentId = 1, Name = "Roofing",
                Start = today.AddDays(12), End = today.AddDays(18),
                BaselineStart = today.AddDays(10), BaselineEnd = today.AddDays(14),
                Progress = 10
            },
            new()
            {
                Id = 5, ParentId = 1, Name = "Electrical",
                Start = today.AddDays(14), End = today.AddDays(20),
                BaselineStart = today.AddDays(12), BaselineEnd = today.AddDays(17),
                Progress = 0
            },
            new()
            {
                Id = 6, ParentId = 1, Name = "Plumbing",
                Start = today.AddDays(14), End = today.AddDays(21),
                BaselineStart = today.AddDays(12), BaselineEnd = today.AddDays(17),
                Progress = 0
            },
            new()
            {
                Id = 7, ParentId = 1, Name = "Interior finish",
                Start = today.AddDays(21), End = today.AddDays(26),
                BaselineStart = today.AddDays(17), BaselineEnd = today.AddDays(22),
                Progress = 0
            },
            new()
            {
                Id = 8, ParentId = 1, Name = "Inspection",
                Start = today.AddDays(26), End = today.AddDays(28),
                BaselineStart = today.AddDays(22), BaselineEnd = today.AddDays(24),
                Progress = 0
            },
        };
    }

    protected override async Task OnAfterRenderAsync(bool firstRender)
    {
        if (firstRender)
        {
            await gantt.ExpandRows(tasks);
        }
    }
}
```